How to assign a Framing Crew to an Element?

Login to COM

Go to Crews

  • Create a Crew. Click here to see how.
  • After the addition of the crew members, the add user icon on the action column will turn green.
  • Next, click on the Assign Element icon (Figure 1).
  • You will be taken to the Assign Element screen. Here you will see a list of elements for which the Framing stage has been toggled and matches the logged in user’s yard (Figure 2).
  • Before you select your elements you can filter the list by yard by using the yard filter on top. (Figure 3)
  • Click on the circular add icon to assign that element to the crew. From the Work Performed dropdown, select work performed (Figure 4).
  • Click on the Finish button to assign elements successfully. After assigning the elements, the Add Element icon on the Crew Management screen will also turn green (Figure 5).

Only Framing Assign Element screen shows which stage has been completed and which one is pending for all the elements. An empty Grey box shows Not Requested, an empty Yellow box shows Not Assigned, a Yellow box with a clock icon shows In Progress.

A Framing user should assign a Framing Crew to an Element after the Excavation stage is completed.

Figure 1
Figure 2
Figure 3
Figure 4
Figure 5

Permissions: Framing Admin and Operational Supervisors