Release Notes
Date | Description |
6/7/19 | New iPad workflow with HR as the ‘Approver’ to submit Gangsheet: 1- Add Crew Management Screen 2- Modify Vehicle Screen so that HR can cost vehicles to Elements 3- Add Timesheet Screen so that HR can add their own time 4- Allow a Crew Leader to be noted for each crew so that the crew so that the crew can be identified in the iPad app. |
6/17/19 | New Request Modules: 1- Add Request Mod for Sawcutting 2- Add Request Mod for Excavation 3- Add Request Mod for Asphalt |
6/17/19 | Add Element Work History |
6/17/19 | 1- Set Element Start Date to the date that a sawcutting crew is assigned. 2- Set Element Substantially Completed Date to the date when the Concrete Request is marked completed. 3- Set Project End Date to the date that the Asphalt Request is marked completed for the last element in the project. 4- Update all dashboard counters based on completed Asphalt Requests. 5- Update Workmap to show Element stage color based on the requested stages. 6- iPad: Remove Crew Timesheet |
8/22/19 | 1- Add ‘Copy Crew’ function 2- Allow Supervisors to complete elements separately within a single Request. |
8/26/19 | 1- Engineer: Add single toggle to ‘Select All Stages’ for an element. 2- Restrict duplicate intersections while creating a New Project. 3- Add hover tooltip for ‘Copy Crew’ function to show crew members. 4- Add PedRamp counter for IFA projects. |
9/9/19 | 1- Project Management: Filter Projects by “My Yard” 2- Project Management: Add accordion panel so that users can quickly view the stage(s) of each Element and Submit a Request 3- Project Management: Allow users to Submit a Request from the Project Management profile page. |
9/9/19 | Workmap: Filter projects by ‘My Yard’ |
9/9/19 | 1- Rename Sub Projects to ‘Elements’ 2- Rename Treatments to ‘PedRamps’ |
9/9/19 | Operational Supervisor Gangsheet: Add vehicles selection. Add Locations: Yard + intersections for assigned crews. |